Pike Library construction behind schedule but moving along

The new $2 million Pike County Library is taking shape as workers welded framing for dormers this week.

The building, on East Harford Street in Milford, was to be done by the end of 2012 but the targeted completion date has been pushed back to March 2013 according to Library Board President Rob Rohner.

At the end of 2011, an excavator discovered an underground tank leaking heating oil on the project land. Both the tank and the contaminated soil were removed, adding added at least $50,000 to the project and a delay while Pennsylvania Department of Environmental Protection wrote a report on the matter and approved the continuation of construction.

This delayed the ordering of materials, and then the delivery of the materials was delayed, ultimately pushing the completion date into next year.

 

This entry was posted in Milford. Bookmark the permalink. Post a comment
We reserve the right to remove any content at any time from this Community, including without limitation if it violates the Community Rules. We ask that you report content that you in good faith believe violates the above rules by clicking the Flag link next to the offending comment or fill out this form.